Week 7 (17/5/2010 - 22/5/2010)


Sat (22/5/2010)


Excavation work to let the RC wall installation work start at the car park area beside TNB substation.




The existing structures are demolished by the hydraulic breaker.


Mr Azizul, my company surveyor is surveying the grid lines for the RC wall.