Sunday, May 23, 2010

Week 7 (17/5/2010 - 22/5/2010)


Sat (22/5/2010)


Excavation work to let the RC wall installation work start at the car park area beside TNB substation.




The existing structures are demolished by the hydraulic breaker.


Mr Azizul, my company surveyor is surveying the grid lines for the RC wall.




Thursday, May 13, 2010

Week 6(10/5/2010 - 15/5/2010)


Construction Safety Policy



Rubbish chute installation


Safety access to enter the tower block


Scaffoldings are erected surrounding the tower block and they are covered with netting to avoid human, rubbish and debris from falling out.



Scaffolding tag


Temporary staircase for the workers climb up to higher level


Mon(10-5-2010)

Today, a hydraulic breaker comes to the site to demolish the existing structures(pilecaps & beams). The body of this hydraulic breaker is same as escavator but the bucket is replaced with a breaker.





Tuesday, May 4, 2010

Week 5(3/5/2010 - 8/5/2010)


Liftcore Wall

Reinforcement work are done to the Liftcore wall.


Steel form to the Liftcore wall are erected.


Braces are also erected to support the steel form.


Concrete casting are done to the liftcore wall.

Liftcore



Mon(3/5/2010)
I went back my hometown on friday after work because saturday no need to work(Labour Day!!!). After coming back from hometown, i have to repeat my daily routine again.

0600 Wake up
0640 Depart to Kajang KTM station
0715 Take KTM to Bandar Tasik Selatan LRT Station
0735 Take LRT
0750 Drop at Hang Tuah LRT Station and walk to IPK,KL
0800 Start working
1000-1030 Minum Pagi
1200 Lunch
1300 Continue working
1500-1530 Hi-tea
1700 Finish work and walk to LRT station
1720 Take LRT
1735 Reach Bandar Tasik Selatan KTM station and wait for the 1743 train(if it's not delayed)
1830 Home Sweet Home


Today is the first day of the tower crane operates!!!

Week 4(26/4/2010 - 30/4/2010)


Anti Termite Treatment


Termicide 38.7 is the latest technology in termite control solution.

It help to identify the termite colony within days and help in total annihilation to the detected colony within one to two months.


The mixing ratio for the pesticide is 130ml/10 liter of water. As you all can see, the pesticide is mixed in the barrel. Then, the water pump will suck it in high pressure and transfer to the sprayer.


It is recommended that 1m square of land is sprayed with 5 liter of mixed pesticide.



Water Proofing

Part A


Component B


Part A and Component B are mixed.



Then, the water proofing material is applied on the Lockup lower ground beam.