Thursday, June 24, 2010

Week 12 (21/6/2010 - 25/6/2010)


The Last Week of My Industrial Training!!!


Progress in this 3 Months...........


The 1st Week - undergoing the construction of Level 3 of the main building



The 7th Week - undergoing the construction of Level 5 of the main building



The 12th Week ( The LAST Week) - undergoing the construction of Level 8 of the main building

Monday, June 14, 2010

Week 10 (7/6/2010 - 12/6/2010)





Retaining Wall At Car Park Area


Excavation work is done.


The existing structures (ground beams, pile caps.....) are demolished by the hydraulic breaker.


The workers are clearing the demolished concrete and reinforcement.


Then, the surveyor will survey and mark out the exact location of the R.C. retaining wall.




The carpenter will erect the formwork to the retaining wall base. Lean concrete is done to the ground. Next, polyethylene(PE) sheet is applied on the lean concrete. Reinforcement work will be done to the retaining wall base.


Concrete casting is done to the retaining wall base.


Then, reinforcement work is done to the retaining wall.


Formwork are erected to the retaining wall.


Bracings and supports are installed to support the formwork.


Concrete casting is done to the retaining wall.


Formwork is dismantled after the concrete dried.


Bituminous material is applied on the retaining wall.


After that, soil backfilling until the required level is done to the retaining wall.


Top view of the retaining wall

Sunday, June 6, 2010

Week 9 (31/5/2010 - 4/6/2010)


Brick Wall Lintel



First, the worker drilled 4 small holes to the beam. Then, stiffeners are installed into the holes and grouted with Hilti Hit.


Reinforcement work is done to the lintel.


Next, formwork is installed.


Concrete casting is done to the lintel.


The finished lintel

Tuesday, June 1, 2010

Week 8 (24/5/2010 - 29/5/2010)


Staircase


First, formwork is sawn to the staircase.


Then, reinforcement work and electrical PVC pipe conduit c/w junction box installation are done to the staircase.


Formwork is done to the steps of the staircase.


The dust, sand, stones etc are blown out from the formwork by using the air compressor before concrete casting.


The staircase after concrete casting


Formwork is dismantled.


Honeycombs are found.


This worker is repairing the honeycombs by special cement.