Thursday, June 24, 2010
Monday, June 14, 2010
Week 10 (7/6/2010 - 12/6/2010)
Retaining Wall At Car Park Area
The carpenter will erect the formwork to the retaining wall base. Lean concrete is done to the ground. Next, polyethylene(PE) sheet is applied on the lean concrete. Reinforcement work will be done to the retaining wall base.
Concrete casting is done to the retaining wall base.
Then, reinforcement work is done to the retaining wall.
Then, reinforcement work is done to the retaining wall.
Sunday, June 6, 2010
Week 9 (31/5/2010 - 4/6/2010)
Tuesday, June 1, 2010
Week 8 (24/5/2010 - 29/5/2010)
Sunday, May 23, 2010
Week 7 (17/5/2010 - 22/5/2010)
Thursday, May 13, 2010
Week 6(10/5/2010 - 15/5/2010)
Construction Safety Policy
Scaffoldings are erected surrounding the tower block and they are covered with netting to avoid human, rubbish and debris from falling out.
Mon(10-5-2010)
Today, a hydraulic breaker comes to the site to demolish the existing structures(pilecaps & beams). The body of this hydraulic breaker is same as escavator but the bucket is replaced with a breaker.
Tuesday, May 4, 2010
Week 5(3/5/2010 - 8/5/2010)
Liftcore Wall
Mon(3/5/2010)
I went back my hometown on friday after work because saturday no need to work(Labour Day!!!). After coming back from hometown, i have to repeat my daily routine again.
0600 Wake up
0640 Depart to Kajang KTM station
0715 Take KTM to Bandar Tasik Selatan LRT Station
0735 Take LRT
0750 Drop at Hang Tuah LRT Station and walk to IPK,KL
0800 Start working
1000-1030 Minum Pagi
1200 Lunch
1300 Continue working
1500-1530 Hi-tea
1700 Finish work and walk to LRT station
1720 Take LRT
1735 Reach Bandar Tasik Selatan KTM station and wait for the 1743 train(if it's not delayed)
1830 Home Sweet Home