Industrial Training

Week 1(5/4/2010 - 10/4/2010)

5-4-2010(Mon)
Today is my first day of Industrial Training. At 9am, I had reported myself at Gainvest Builders (M) Sdn Bhd office which is located at Kelana Jaya. Then, I moved myself to the construction site which is located just beside Jalan Hang Tuah. It is a project of extension office building of the Kuala Lumpur Police Headquarter.



Column

This is the making of the column K/12 at level 2.First, the bar binders insert the links to the starter bar from the level 1 column. Then, they tied the steel bars to the starter bars.


The column's steel bar that already tied with the links.


Next, the labours start to fix the column's steel formwork.


After that, the labours will fix the support to the steel formwork to make sure the column is in straight position.


Finally, concrete casting is done to the column. The steel formwork can be remove on the next day.


This is the column after removing the steel formwork.